500 Capability Green
Project snapshot

LOCATION

Luton

client

Arkay Contractors

contract value

£850,000

duration

20 weeks

programme

Curtain wall refurbishment

Apex Developments

Courtland Contracts

Daisy
Rose

DML
Finishes

Kingfisher Electrics

square
one

Project overview

The works involved a full curtain wall refurbishment to a large business unit in Luton, preparing the building for its new tenant, TUI. The existing system dated back to the 1980s and could not be fully identified, which created technical uncertainty around replacement components and long-term performance. The client required a practical route to remediate the façade while retaining the original framing.

Initial site conditions included ageing glazing, historic detailing, and a system with no accessible technical record. Weather created further pressure, with rain, ice, and snow affecting progress through November. Weekly coordination and phased working by elevation helped maintain control across the programme.

our approach

Early engagement between the contractor, designer, and Square One shaped a clear technical direction. A full sample and mock-up stage was completed before works began, followed by pre-construction water testing to benchmark performance. This ensured the retained framing could support the new system components.

The project was sequenced by elevation to align with scaffold movements. Material choices were driven by a mix of experience and sample validation, ensuring compatibility with the existing frames. Access was delivered using a combination of scaffold and MEWPs. A joint QA process between the contractor and client governed inspections, documentation, and sign-off.

Explain how the team planned, prepared and coordinated the works.
Describe any design considerations, sequencing, safety requirements or challenges overcom

work delivered

• Sample and mock-up installation
• Water testing to validate both the mock-up and the main works
• Technical design assistance and problem solving
• Material supply and fabrication
• Strip-out of existing components
• Installation of new curtain wall system elements
• Welfare provision
• Weekly reporting to track progress and sequencing
• Health and safety compliance across the package
• Waste removal and site skips
• Full quality assurance and final handover

project gallery
project outcome

The curtain wall was fully refurbished using new components including glazing, accessories, tapes, seals, pressure plates, cappings, and perimeter silicone. The building achieved the required U-value for its operational use. External appearance was significantly improved, and the system is now watertight and performing as intended. The project delivered strong compliance outcomes with clear technical justification and a controlled installation process.

group collaboration

This project benefitted from close coordination across contractors.

Unified Technical Planning

Joint input across contractor, designer, and Square One set a strong benchmark through early testing

Integrated Sequencing

Elevation-by-elevation planning aligned with scaffold movements and kept progress steady

Shared Quality Controls

A combined QA process ensured consistent inspections and reduced the risk of defects.